We have a renewals programme in place to effectively maintain our 1,429 properties, enabling us to continuously improve our properties for residents.
The planned works for 2024-2025 are below, all dates are estimated and are subject to alteration.
We will contact residents impacted by works and regularly update on progress and start dates.
Cyclical Painting Addresses
- (September-March)
- Rokeby Mews/Rokeby Avenue Rosedale Grove
- Junella Close
- Quilter Avenue
- The Jacobs Homes
Windows/Doors
- (August – March)
- Broadway Manor (pending planning permission)
- Broadway Lodge
- Broadway Cottages
- East Grove/Priory Grove
Kitchens
- (September – February)
- Barham Road
- Northumberland Avenue
Communal Kitchens
- (January – February) Richardsons Court
- Christopher Pickering Lodge
Bathrooms
- (April – November)
- Malin Lodge
Roofline
- (September – November) Buttercup
- Endike Lane
Scheme Heating Replacements
- (January – March)
- Christopher Pickering Lodge
- Scheme Commercial
Boiler Replacement
- (July)
- Ada Holmes Circle
Passenger Lift replacements
- (January – March)
- Ada Holmes Circle
- Broadway Manor
For more information please call 01482 223783.